A battery doesn’t keep your lights on in a power cut just because it’s full. Whether it does, how much of the house it can run, and whether you even notice the switch depends on the backup hardware around it. This guide explains what whole home battery backup really means in the UK, why the switchover time is measured in milliseconds, and how Tesla Powerwall 3, Sigenergy and the other leading systems compare on the numbers their own manufacturers publish.
At a glance
0 msLoad-side switchover Sigenergy, Enphase and Anker state, under their test conditions
13.5 kWhEach Tesla Powerwall 3, up to 94.5 kWh in a system
100 ASingle-phase rating of the Tesla, Sigenergy and Enphase gateways – not the backup power
Earth electrodeIsland mode needs a consumer earth electrode – new, or a suitable existing one
- An ordinary solar or battery system switches off in a power cut. Backup needs a gateway or backup box.
- “Whole home” means every circuit on the backed-up board, within the inverter’s and battery’s power limits. It is not unlimited capacity.
- Tesla’s datasheet gives no switchover time; Sigenergy, Enphase and Anker quote 0 ms under stated conditions.
Do solar batteries work in a power cut?
Not on their own. Grid-connected solar and battery inverters are installed under the G98 and G99 connection standards, which require the generator to disconnect automatically from the network when the grid supply is lost. So a standard system goes dark in a power cut, even on a sunny day with a full battery.
To keep running, the system needs to separate your home from the grid and then supply it by itself. Engineers call this island mode, and it takes extra hardware. The IET’s Code of Practice for Electrical Energy Storage Systems and the network operators’ G99 standard describe three things an installation needs to run in island mode:
- An island mode isolator that disconnects your live and neutral conductors from the grid
- A neutral-earth bond relay that creates a neutral for the island
- A consumer earth electrode, because BS 7671 says a generating source running as a switched alternative to the public supply in a TN system cannot rely on the network’s earthing. An existing electrode, such as one from a TT system, can be used where it meets the design requirements.
In practice the first two are usually built into a manufacturer’s backup gateway, backup box or EPS box. The earth electrode is separate: your electrician either installs one or confirms that an existing electrode meets the design requirements. That is why backup is something to plan at the start, not a switch you flip later.
What changed in 2026
The wiring rules moved on this year. BS 7671:2018+A4:2026, published in April 2026, adds a new Chapter 57 for stationary secondary batteries and requires a stationary battery to be treated as a generating set rather than a load. The previous version, BS 7671:2018+A2:2022+A3:2024, was withdrawn on 15 October 2026, so installations designed from that date follow A4. In July 2026 the IET’s Wiring Matters set out how automatic disconnection of supply works in an island-mode home. The island runs as a TN system referenced to a local earth electrode, and the neutral-earth link is made only while the home is disconnected from the grid. Because inverters supply only limited fault current, an RCD is required on the load side of that link so that faults are disconnected within BS 7671’s required times. The IET Code of Practice is now in its third edition (2024), which updated the requirements for island mode isolators. The same three building blocks appear in the G99 standard (Figure 8.13) and in the IET’s July 2026 guidance.
Ofgem measures every electricity distribution network operator on how often its customers lose power and for how long. In its 2024–25 report it said several companies were penalised under its Interruptions Incentive Scheme for missing their targets, bringing cumulative penalties over the first two years of RIIO-ED2 to £50.9m.
Whole home battery backup vs partial backup
There are two ways to wire a backup system, and the difference decides what stays on.
Whole home backup
The gateway feeds your main consumer unit
- Every circuit on the backed-up board can stay live, within the system’s power limits
- Usually no separate essentials board to wire
- Needs an inverter big enough for what you switch on
- The battery drains faster if everything is running
Partial backup
Only an essential-circuits board is backed up
- Lights, fridge, router and boiler stay on
- The oven, shower and other big loads go off
- A smaller inverter can cope
- The battery lasts longer
Both are legitimate choices, and the leading manufacturers document both. Tesla’s Powerwall 3 datasheet shows a whole home layout and several partial ones. Sigenergy’s HomeMax gateway lists support for “both whole home backup & partial home backup”. Anker’s installer guides for the SOLIX X1 Power Dock Pro, single phase and three phase, set a simple dividing line: whole-home backup requires a main circuit breaker rated at 63 A or below; for ratings above 63 A, partial home backup must be used. Check your main fuse rating before planning whole-home backup with Anker.
The deciding factor for whole home is usually power, not storage. Whole home backup keeps supply to the circuits on the backed-up consumer unit, but what actually runs depends on:
- the inverter’s continuous and short-term peak output
- how fast the battery can discharge
- how much is switched on at the same time
- the starting current of motors such as pumps and compressors
- the installation design, and any load management or load shedding
An electric shower, oven or heat pump can draw more than a smaller home inverter supplies. If the loads exceed what the system can deliver, it can’t hold them all, however much energy is in the battery.
A gateway’s rating is not your backup power. Tesla’s Backup Gateway 2 is rated 100 A on a single-phase supply, but each Powerwall 3 supplies up to 11.04 kVA continuously. Sigenergy’s HomePro SP-F is rated 100 A and 22 kW at the grid, yet its inverter connection is rated 55 A and 12 kW, single-phase energy controllers run from 3.0 to 12.0 kW, and each SigenStor BAT 10.0 module discharges at up to 4.6 kW. Enphase’s IQ System Controller 3 carries up to 100 A of load, while each IQ Battery 5P supplies 3.84 kVA. In a power cut, the continuous power you can draw is capped by the smallest of three things: the inverter’s output, the combined discharge rating of all the installed battery modules (plus any solar still generating), and the gateway rating.
Switchover time: why milliseconds matter
When the grid fails, there is a gap between the supply dropping and the battery taking over. That gap is the switchover time, and it is measured in milliseconds (ms): thousandths of a second. It decides whether a power cut is something you notice.
- 0 ms (load-side): the manufacturer states no break on the backed-up circuits under its test conditions.
- Up to about 20 ms: a very short gap. Lights may flicker. Whether a device notices depends on its own power supply, so many carry on and some sensitive electronics may restart.
- Seconds: a short blackout. Anything without its own battery – the Wi-Fi router, a desktop computer, boiler controls – switches off and back on.
| System | Stated switchover | The conditions in the small print |
|---|---|---|
| Sigenergy Gateway + Energy Controller + battery | 0 ms load-side disruption | Needs a Sigenergy gateway, controller and battery; tested with the controller’s nominal power higher than the backup loads |
| Enphase IQ System Controller 3 + IQ Battery | 0 ms load transition | Installed IQ Battery power must exceed the loads; may vary with grid conditions (preliminary UK datasheet) |
| Anker SOLIX X1 + Power Dock Pro | 0 ms load-side | Only with X1 power and battery modules, and the X1 power module’s rated power must exceed the backup loads; the X1 inverter alone quotes under 10 ms |
| Fox ESS H1 Gen 2 (inverter EPS port) | Under 20 ms | The inverter’s own EPS output, for the circuits wired to it |
| Fox ESS EPS Box SP (whole home) | Under 3 seconds | Automatic switching time stated in Fox’s EPS Box SP manual |
| Huawei SmartGuard (three phase) | 20 ms or less | With Huawei MAP0 inverters once seamless switching is enabled (off by default); up to 100 ms with M1 and MB0 inverters |
| SolarEdge Home Backup Interface (single phase) | Under 3 seconds | On-grid to off-grid switchover |
| SolarEdge Home Backup Interface (three phase) | Under 10 seconds | Depends on local grid settings |
| Tesla Powerwall 3 + Backup Gateway 2 | Not published | The datasheet says the Gateway detects outages and provides “quick backup power” |
Every “0 ms” figure comes with conditions, and the most important one is power: the battery system must be able to supply more than the loads running at the moment of the cut. A stated switchover time is a manufacturer specification measured under its own test conditions, not a guarantee that every appliance or computer will run uninterrupted in every situation. Size the system for what you want to keep on, and the headline figure means something.
Tesla Powerwall 3 vs Sigenergy for backup
These are the two systems most often shortlisted for whole home backup, and they get there in different ways. Tesla builds the battery and a hybrid inverter into one unit and adds a separate Backup Gateway 2. Sigenergy builds a modular stack: an energy controller (the inverter), battery modules stacked on it, and a separate gateway.
| Tesla Powerwall 3 | Sigenergy SigenStor | |
|---|---|---|
| Backup device | Backup Gateway 2 (required for backup) | Sigen Energy Gateway (HomePro SP-F or HomeMax) |
| Stated switchover | Not published | 0 ms load-side (with conditions) |
| Gateway rating | Backup Gateway 2: 100 A on a single-phase supply, 80 A per phase on three phase | HomePro SP-F: 100 A, 22 kW, single phase (inverter connection 55 A, 12 kW) |
| Battery | 13.5 kWh per unit; up to 4 Powerwall 3 plus 3 Expansions in total per system, 94.5 kWh | 1 to 6 battery modules per controller |
| Inverter power | Up to 11.04 kVA per Powerwall 3 (Expansions add storage, not output power); 44 kW AC continuous is the combined rating of a four-Powerwall system, and backup through one single-phase Gateway 2 is limited to 100 A | Single phase controllers 3.0–12.0 kW; three phase 5.0–30.0 kW |
| Heavy loads | Starts loads up to 185 A LRA (locked rotor amps) | Up to 150% peak output for 10 seconds off-grid (less on the largest models) |
| Three-phase homes | Powerwall 3 is a single-phase unit; the UK Gateway 2 backs up a selected single phase and disconnects all phases automatically | Three-phase controllers with a 380/400 V backup output, and the HomeMax TP three-phase gateway |
| Generator | Not covered on the datasheet | HomePro SP-F has a Smart Port for a generator (12 kW nominal) with 2-wire start |
Where Tesla stands out
The Powerwall 3 is simple to specify: one unit holds 13.5 kWh and the inverter, and Tesla says a single Powerwall 3 can start heavy loads rated up to 185 A LRA – the inrush current motors such as pumps and compressors draw when they start. Systems scale to four Powerwall 3 units and three Expansion units in total, storing 94.5 kWh and rated at 44 kW AC continuous between them. One Powerwall 3 on its own supplies up to 11.04 kVA. In a power cut, a single-phase home is still limited by the 100 A Backup Gateway 2; 100 A at 230 V is about 23 kW. Tesla’s datasheet lays out a whole home arrangement and several partial ones, so your installer has a clear reference.
Where Sigenergy stands out
Sigenergy puts a figure on its datasheet where Tesla’s has none: 0 ms load-side disruption, provided the gateway, controller and battery are all Sigenergy and the controller’s nominal power exceeds the backup loads. Its HomePro SP-F gateway (marked Preliminary on its datasheet) is rated at 100 A and 22 kW, includes a bypass circuit, and has a Smart Port for a generator with 2-wire start. Its HomeMax gateway also lists support for generators, heat pumps and other controllable loads. The modular stack takes one to six battery modules per controller, so capacity can grow later.
The three-phase question
If your home has a three-phase supply, check this before choosing. Powerwall 3 is a single-phase unit, and Tesla’s UK Backup Gateway 2 datasheet says backup covers a selected single phase, with automatic disconnection of all phases. Sigenergy makes three-phase energy controllers whose backup output is 380/400 V three phase, and a three-phase HomeMax TP gateway. Huawei’s SmartGuard is a three-phase backup box rated at 63 A. Anker’s three-phase Power Dock Pro (63-T-EU) supports whole home backup only where the main breaker is rated 63 A or below.
Other whole home backup systems compared
Tesla and Sigenergy lead for whole home backup, but they aren’t the only options. Here is how the other main systems we supply handle it.
Enphase IQ System Controller 3
Enphase uses microinverters and AC batteries, with the IQ System Controller 3 INT as the backup switch. It includes an automatic transfer switch, carries up to 100 A of backup load on a single-phase connection or 80 A per phase on three phase, and its preliminary UK datasheet states a load transition time of 0 ms when the installed IQ Battery power exceeds the loads. Its IQ Battery 5P holds 5.0 kWh of usable energy and supplies up to 3.84 kVA continuous on single phase, or 1.28 kVA per phase on three phase.
Anker SOLIX X1
Anker’s X1 single-phase hybrid comes in 3.68 to 6 kW and takes 5 to 30 kWh of battery, with a 10-year limited warranty. The inverter alone quotes a switch time under 10 ms, and each 5 kWh battery module charges and discharges at up to 3 kW. Add the Power Dock Pro backup hub (sold as Power Dock Pro ATS) and Anker states 0 ms load-side backup switching, provided X1 power and battery modules are installed and the X1 power module’s rated power exceeds the backup loads.
Fox ESS
Fox ESS’s H1 Gen 2 hybrid inverters have an EPS (emergency power supply) output with a stated switch time under 20 ms. That is the inverter’s own backup port, which supplies the circuits wired to it. For whole home backup, Fox’s single-phase EPS Box SP takes up to 100 A and switches automatically between on-grid and off-grid, working with H1-G2, KH and EVO inverters. Fox’s EPS Box SP manual gives its automatic switching time as less than 3 seconds, so expect a brief blackout before the house comes back on. The box’s inverter ports are rated 63 A, and Fox says the load must not exceed the inverter’s maximum off-grid output.
SolarEdge Home Hub
SolarEdge’s single-phase Home Hub inverters pair with the single-phase Home Backup Interface for services up to 100 A and up to three single-phase inverters. The interface states an on-grid to off-grid switchover of under 3 seconds, so expect a brief blackout before backup power comes on. On SolarEdge’s standard single-phase Home Hub datasheet, rated backup output is 6,000 W across the 2.5 to 6 kW models and 10,000 W on the 8 and 10 kW models, and total battery discharge is limited to the inverter’s rated AC power. Ratings differ between Home Hub versions, so check the datasheet for your exact model. The three-phase Backup Interface is rated 3 × 63 A and states a switchover of under 10 seconds, depending on local grid settings.
Huawei SmartGuard
Huawei’s SmartGuard-63A-T0 is a three-phase backup box rated at 63 A. It states a switchover of 20 ms or less with Huawei’s MAP0 hybrid inverters once seamless switching is enabled, and up to 100 ms with its M1 and MB0 inverters. Its datasheet notes that seamless switching is off by default and has to be enabled.
Whole home battery backup vs a generator
A battery and a generator solve the same problem in different ways, and some systems now combine them. A battery backup system takes over automatically, and the fastest state no load-side break at all. A generator can keep running for as long as it has fuel, which matters in a long outage when there is little sun to recharge a battery.
If you want both, check the backup gateway. Sigenergy’s HomePro SP-F has a Smart Port for a generator rated at 12 kW nominal, with 2-wire start, and its HomeMax gateway lists generator support and an uninterrupted supply from solar and battery, grid or generator. A generator must be connected through equipment designed for it, never back-fed into the house, and that is a job for your installer.
How much battery do you need for backup?
Two numbers decide what a backup system can do, and they answer different questions.
- Inverter power (kW): what can run at once Add up what you want running together in a power cut. The inverter must supply more than that, with headroom for the starting current of motors such as pumps and compressors.
- Battery capacity (kWh): how long it lasts Divide the usable kWh by the power your home draws on average. Halve the load and the battery lasts roughly twice as long.
- Solar: whether it refills A system that can keep its solar running in island mode can recharge the battery on a bright day during a long outage. Sigenergy’s gateway lists solar, battery, grid and generator among the sources it can switch between.
Check the battery’s discharge limit as well: a battery can only deliver its rated discharge power, which may be below the inverter’s rating. Anker’s X1 battery module, for example, is limited to 3 kW and a SigenStor BAT 10.0 module to 4.6 kW, so you may need more than one module to use the inverter’s full output.
For most homes, the practical approach is to list the circuits you can’t do without, decide whether you need the whole house or just those, and size the inverter for the first question and the battery for the second.
Installing whole home backup: earthing, DNO and MCS
- Earthing. As above, island mode needs an island mode isolator, a neutral-earth bond relay and a consumer earth electrode, either new or an existing electrode that meets the design requirements. Your installer designs this to BS 7671:2018+A4:2026, the IET Code of Practice for Electrical Energy Storage Systems and the G99 earthing arrangements.
- Your network operator. Battery systems are connected under the G98 or G99 standards, so your installer notifies or applies to your Distribution Network Operator (DNO). A system designed to run in island mode is outside the scope of G98, so it is handled under G99 even when it is small. If it is no bigger than 16 A per phase, its generating equipment must be fully type tested.
- MCS. MCS’s battery installation standard, MIS 3012:2025, already applies to MCS-certified installers. Separately, MCS consulted on a proposed Battery Storage Product Standard (MCS 042) from 13 October 2026; the consultation closed on 10 November 2026. The standard would set requirements for the battery products themselves. It is a draft under development, not yet a requirement, and MCS has not announced an implementation date.
- A qualified installer. Backup touches the incoming supply, the earthing and the main consumer unit. It is a job for an electrician experienced in battery storage.
Whole home backup systems we supply
Live prices and stock, ex VAT:
Whole home battery backup questions
Do solar panels work in a power cut?
Not on a standard system: grid-connected inverters must disconnect when the grid fails. With a backup gateway or backup box designed for island mode, a system can keep supplying your home, and some can keep the solar running too.
What is a good switchover time for home backup?
The faster the better. Sigenergy, Enphase and Anker state 0 ms load-side under their test conditions. That is a manufacturer specification, not a guarantee for every device in every situation. Up to about 20 ms is a very short gap: lights may flicker, many devices carry on and some sensitive electronics may restart. A few seconds means devices without their own battery switch off and restart.
Can Tesla Powerwall 3 back up my whole house in the UK?
It can back up every circuit on your main consumer unit with Backup Gateway 2, which Tesla says is required for backup, and its datasheet shows whole home and partial layouts. What actually runs depends on the Powerwall’s output (up to 11.04 kVA per unit), how much is switched on at once and the starting current of motors, so your installer sizes the system and any load management for your home. On a three-phase supply, the UK Gateway 2 backs up a selected single phase.
Powerwall 3 or Sigenergy: which is better for backup?
They suit different homes. Powerwall 3 is one integrated unit with strong motor-starting ability and a published multi-unit maximum of 94.5 kWh. Sigenergy publishes a 0 ms load-side switchover under stated test conditions, has a Smart Port for a generator on its HomePro SP-F gateway, and offers three-phase controllers with a three-phase backup output.
Do I need an earth rod for battery backup?
You need a consumer earth electrode if the system runs in island mode. The IET Code of Practice and the G99 standard call for one, because BS 7671 says a generating source running as a switched alternative to the public supply in a TN system cannot rely on the network’s earthing. It does not have to be a new rod: an existing electrode, such as a TT earth rod, can be used if it meets the design requirements.
Can I add backup to an existing battery later?
It depends on whether the manufacturer makes a backup gateway or box for your system, and it means work on the incoming supply and earthing. Check with the manufacturer and your installer before buying.
Planning whole home backup?Build a system with a battery and backup gateway that work together, priced live.
Sources
- Tesla, Powerwall 3 datasheet (UK), and the Backup Gateway 2 datasheet on our Gateway page.
- Sigenergy datasheets for the Gateway HomePro SP-F, Energy Controller and HomeMax gateway, on our HomePro gateway page.
- Enphase, IQ System Controller 3 INT datasheet, on our IQ System Controller page; IQ Battery 5P on our IQ Battery page.
- Anker SOLIX X1 single phase datasheet, and the Power Dock Pro preliminary datasheet and single- and three-phase installer guides, on our Power Dock Pro page.
- Fox ESS H1/AC1 Gen 2 datasheet and EPS Box SP datasheet and user manual, on our H1 Gen 2 page and EPS Box page.
- SolarEdge Home Backup Interface (single and three phase) and Home Hub datasheets, on our single-phase and three-phase Backup Interface pages.
- Huawei SmartGuard 3PH datasheet, on our SmartGuard page.
- IET, Automatic disconnection of supply for island mode prosumer electrical installations, Wiring Matters 110, July 2026.
- IET, Island mode earthing arrangements, Wiring Matters 84 (on the second edition of the Code of Practice), and the Code of Practice for Electrical Energy Storage Systems, 3rd edition (2024).
- SELECT, Amendment 4:2026 What’s New (withdrawal date of the previous version of BS 7671).
- IET, IET and BSI publish Amendment 4 (2026) to BS 7671:2018, 15 April 2026.
- Energy Networks Association, EREC G99 Issue 2 (section 9.6, island mode) and EREC G98 Issue 2, 2025.
- Ofgem, RIIO-2 Electricity Distribution annual report 2024–25.
- MCS, MCS 042 consultation announcement, Consultations and MIS 3012 Battery Installation Standard.
- Header photo: Stephen Craven, CC BY-SA 2.0, via Wikimedia Commons.